Our existing infrastructure is more than twenty years old, and we have now outgrown it. So, the time has come to future-proof Staglands for the next generation.
We are excited to share more details about our new Cafe & Main Entrance redevelopment with you…
LATEST UPDATE W/C 18 Aug 2025
NEW MAIN ENTRANCE AND CAFE NOW OPEN!
After many months of dreaming, planning, and hard mahi, our brand-new main entrance building is now officially open! 💚
This beautiful new space marks a huge milestone for us. Please come, explore, and make yourself at home in our stunning new space.
Note: Temporary exit still operating for a few more weeks - please follow 'Temporary Exit' signage.
Stage 1: NOW COMPLETED
Our cafe has been significantly extended, with the following work completed:
• Increased seating inside for visitors.
• Expansive new deck leading to re-landscaped area in front of the café
• Completely remodelled kitchen and serving area.
Stage 2: NOW COMPLETED
The construction of an expansive new entrance building with impressive trusses framing the entrance which has been designed to be reminiscent of a historic woolshed is now complete!
Stage 3: CURRENTLY IN PROGRESS
Upgraded toilets - target completion date September 2025
Brand-new Staglands Shop, target completion date December 2025.
Impact on our visitors…
• Temporary exit– please follow signage.
• Some paths will be closed – please follow signage.
• Portaloos available whilst toilets are being upgraded.
Thank you for your understanding whilst we undertake the final stages of this project.